The objective of the Post Contract Implementation Performance is to understand the manufacturing process after the contract is signed and the project is going through design to delivery.
SOLUTION
The solution was required to build a powerful visualization for executives to view the on-time delivery metrics for active projects on keys milestones like:
Design Freeze
Order Entry
Received on Site from Manufacturing
Received on site – Resale
Installation Complete
Beneficial Use
SUCCESS CRITERIA & BUSINESS VALUE
The report and the data integration layer was heavily used at the level of CEO, PMO and Executive committee to answer questions.
How the gates are working through the design to order entry to manufacturing etc.?
How much percentage of the project is behind schedule per each week?